Challenge
To design and install a CHP plant capable of generating 55,000kg/hour or 34 MW of heating steam to service the needs of the building forming the newly completed Foresterhill Health Campus Energy Centre.
Solution
Installation of a three Cochran Dual Fuel Boilers and one Waste Heat Recovery unit, working alongside an existing Gas Turbine and wood chip-fired Biomass Boiler.
Result
The facility’s three Cochran boilers and a biomass boiler have enabled the Campus to be completely self-sufficient in terms of heating. It also generates 90% of its electricity requirement using a gas turbine. The Cochran Heat Recovery Boiler scavenges the exhaust heat of the turbine to generate additional ‘free’ steam.